Contract disputes

First consultation free of charge (Mon–Fri, 9:00–18:00)

Call +380 (97) 158-30-28

A contract dispute usually begins long before court – with loose wording in the contract itself. We work both at the drafting stage and once the conflict has arisen.

When to get in touch

  • a counterparty is not performing, or is performing improperly
  • a contract needs to be terminated or varied
  • a contract is being challenged, or there are grounds to have it declared invalid
  • the circumstances the parties assumed when contracting have changed substantially
  • a counterparty has paid late and the debt, penalty interest, inflation adjustment and three percent per annum need to be calculated

Recognise your situation?

First consultation free of charge (Mon–Fri, 9:00–18:00). The fee for further work is agreed in writing before it begins – how we calculate fees.

Call +380 (97) 158-30-28

What the lawyer does

  • analyses the contract and records the breach
  • prepares the letter of demand and negotiates a settlement
  • prepares a claim for performance, termination or a declaration of invalidity
  • makes the case for varying or terminating the contract on a substantial change of circumstances
  • calculates and recovers losses and contractual penalties
  • advises on contractual risk at the drafting stage

Breach of contract and liability

  • An obligation must be performed properly in accordance with the contract and the law and, where these are silent, in accordance with business custom (part 1 of Article 526 of the Civil Code). A breach is non-performance or performance in breach of the terms (improper performance) (Article 610 of the Civil Code).
  • The consequences of breach may include unilateral withdrawal from the obligation (where the contract or the law allows it) or termination of the contract, a change in its terms, payment of a contractual penalty, and compensation for losses and non-pecuniary damage (part 1 of Article 611 of the Civil Code).
  • The party in breach is liable if at fault, unless the contract or the law provides otherwise; it is for that party to prove the absence of fault (parts 1 and 2 of Article 614 of the Civil Code). Liability is excluded by accident or force majeure, but not by the counterparty’s failure to perform, the absence of goods on the market or the debtor’s lack of funds (Article 617 of the Civil Code).

Losses, contractual penalties, inflation adjustment and three percent per annum

  • Losses comprise actual losses and lost profits; they are compensated in full unless the contract or the law provides otherwise (parts 2 and 3 of Article 22 of the Civil Code). The creditor must prove the amount of the losses; when lost profits are assessed, the steps the creditor took to obtain the income are taken into account (parts 2 and 4 of Article 623 of the Civil Code).
  • A contractual penalty may take the form of a fine (a percentage of the obligation not performed) or penalty interest (a percentage of the overdue monetary obligation for each day of delay) (parts 2 and 3 of Article 549 of the Civil Code). For late payment of a monetary obligation, the debtor pays, at the creditor’s request, penalty interest at twice the National Bank of Ukraine discount rate, unless the contract sets a lower rate (part 3 of Article 549, second paragraph, of the Civil Code).
  • The court may reduce a contractual penalty if it substantially exceeds the losses, and where there are other significant circumstances (part 3 of Article 551 of the Civil Code).
  • Inability to perform a monetary obligation does not release the debtor from liability. A debtor who pays late must, at the creditor’s request, pay the debt adjusted for inflation for the whole period of delay and three percent per annum, unless the contract or the law sets a different rate (Article 625 of the Civil Code).

Termination and variation of the contract

  • Unilateral withdrawal from an obligation or unilateral change of its terms is not allowed unless the contract or the law provides otherwise (Article 525 of the Civil Code). Where a right of unilateral withdrawal exists, the contract is terminated or varied accordingly once it is exercised (part 3 of Article 651 of the Civil Code).
  • The court varies or terminates a contract at the request of one party in the event of a material breach by the other – where, as a result of the damage caused, the party is largely deprived of what it was entitled to expect – and in other cases provided by the contract or the law (part 2 of Article 651 of the Civil Code).
  • The obligation is changed or ends from the moment of agreement or, where done by the court, from the day the judgment takes legal effect; what was performed before that moment is, as a rule, not returned. If the contract is terminated because of a material breach, the other party may claim the losses caused by the termination (parts 3–5 of Article 653 of the Civil Code). Variation or termination is made in the same form as the contract (Article 654 of the Civil Code).
  • On a substantial change of circumstances, the court terminates the contract only where all four conditions in part 2 of Article 652 of the Civil Code are met together, and varies it only in exceptional cases (part 4 of Article 652). On termination, the court, at a party’s request, allocates the costs incurred fairly (part 3 of Article 652 of the Civil Code).

Invalidity of a contract

  • A contract is invalid where, at the time it was made, the requirements as to its content, the parties’ legal capacity, free expression of will, its being aimed at real legal consequences, and children’s rights were not met (part 1 of Article 215 and parts 1–3, 5 and 6 of Article 203 of the Civil Code).
  • A void contract is invalid by operation of law, with no need for a court declaration; a voidable contract is declared invalid by the court on the claim of a party or another interested person (parts 2 and 3 of Article 215 of the Civil Code).
  • On invalidity, each party returns everything it received or, if that is impossible, compensates its value; losses and non-pecuniary damage are compensated by the party at fault (parts 1 and 2 of Article 216 of the Civil Code).

Time limits for going to court

  • The general limitation period is three years (Article 257 of the Civil Code). For claims to recover a contractual penalty (fine or penalty interest), it is one year (clause 1 of part 2 of Article 258 of the Civil Code).
  • Claims for the principal debt and for the penalty should therefore be assessed separately: the period for the penalty expires sooner. More on enforcement on the page “Debt recovery”.

Legal basis

Freedom of contract and the general rules are set out in Articles 626 and 627 of the Civil Code of Ukraine; variation and termination in Article 651, and on a substantial change of circumstances in Article 652. The consequences of breach of an obligation are set out in Article 611, and compensation for losses in Article 22. Proper performance is governed by Article 526, the prohibition of unilateral withdrawal by Article 525, the concept of breach by Article 610, fault and release from liability by Articles 614 and 617, compensation for losses caused by breach by Article 623, liability for monetary obligations by Article 625, contractual penalties by Articles 549 and 551, the consequences and form of variation or termination by Articles 653 and 654, invalidity of transactions by Articles 203, 215 and 216, and limitation periods by Articles 257 and 258 of the Civil Code.

Legislation and case law are updated over time; this page reflects the position as of November 2026.

Frequently asked questions

Can a contract be terminated unilaterally?

Only in the cases provided for by the contract or by law (Article 525 and part 3 of Article 651 of the Civil Code). Otherwise, by agreement of the parties or by court decision at the request of one party, in particular in the event of a material breach by the other party (parts 1 and 2 of Article 651 of the Civil Code).

Is a change of circumstances a ground for revisiting a contract?

Where the combination of conditions in Article 652 of the Civil Code is met, the court may vary or terminate the contract.

What can be recovered if a counterparty pays late?

The principal debt adjusted for inflation for the whole period of delay and three percent per annum (unless the contract sets a different rate) (Article 625 of the Civil Code), as well as any contractual penalty provided by the contract or the law, and losses (Articles 549, 611 and 623 of the Civil Code). The limitation period for a penalty claim is one year (clause 1 of part 2 of Article 258 of the Civil Code).

Does lack of funds or a supplier’s failure to perform release the debtor from liability?

No. The counterparty’s failure to perform, the absence of the necessary goods on the market and the debtor’s lack of funds are not regarded as an accident releasing it from liability (Article 617 of the Civil Code); and a debtor is always liable for inability to perform a monetary obligation (part 1 of Article 625 of the Civil Code).

Need legal assistance? Call us or leave a request – a lawyer will contact you and explain what to do in your situation.

How we work

  1. You submit a request

  2. We analyse your situation

  3. We agree a strategy with you

  4. We protect your interests

Similar services

  1. Compensation for material and moral damage
  2. Commercial disputes
  3. Bankruptcy and insolvency
  • 2020

    year founded

  • 9

    attorneys on the team

  • 11

    practice areas

  • 24/7

    urgent legal assistance

Have a similar situation? First consultation free of charge (Mon–Fri, 9:00–18:00).

Call